AI boom leaves network operators waiting up to 18 months for kit

The Register

Source published: Site published:

Original article · فارسی

Prices for optical networking equipment have risen by around 50 percent this year as phone and internet companies compete with datacenters for parts, according to RETN.

Dan RobinsonDanRobinsonIT INFRASTRUCTURE REPORTER
Published

The growth of AI datacenters is pushing up the prices of optical networking equipment and making delivery times much longer. Some orders now take as long as 18 months to arrive, according to network operator RETN.

RETN says network operators and telecommunications companies are now competing directly with AI datacenters for chips and other parts.

As Reg readers may know, memory prices have risen by four or five times over roughly the past year. But RETN says optical networking equipment prices have gone up by around 50 percent since the start of 2026. Delivery times are an even bigger problem. Equipment that once arrived within three months now takes 12 to 15 months. Some orders take as long as 18 months.

The situation is as bad as, or even worse than, the shortages during the pandemic. At that time, chip shortages stopped network equipment makers from filling orders. The problem now is that demand from the AI boom is greater than the available supply.

In its report, "AI, Connected," RETN says developers building datacenters outside established datacenter areas may need to bring in network companies two to five years before the sites open.

RETN says the sudden demand for network equipment from large cloud companies and AI datacenter sites is only part of the problem. Shortages of raw materials and skilled workers, limits on energy supplies, political tensions between countries, and transport and delivery problems are making things worse.

However, RETN admits that many network companies made the situation harder by putting off network upgrades in the past to save money. They can no longer avoid this work, and now they must do it at a very difficult time.

The report says having several different network routes is now essential. In the past, customers were happy with two routes to faraway destinations. Now they expect network operators to provide four or more backup routes.

The goal is to stop one failure from bringing down important services. But having several connections only helps if they do not share the same physical weak points, such as the same underground ducts or cable routes. RETN says a circuit with a separate route might cost €1,800 ($1,975) per month instead of €600 ($658). However, an outage could cost much more.

RETN also says AI datacenters are moving away from towns and cities to remote areas. These places may offer more suitable land, electricity and water. Large cloud companies are building in Nordic countries, where land is affordable, the weather is cooler, and plenty of renewable energy is available.

But remote sites may not have the fiber cables needed to connect them to other datacenters and customers. The Register reported on this problem earlier this year.

When datacenters are close to cities, developers often pay to build their own fiber connections. This usually adds only a few percent to the total project cost. But building connections over much longer distances is harder to justify. Network companies are understandably unwilling to build a long-distance route just to serve one remote site.

Some developers are willing to pay for this. RETN says a major cloud provider is looking into turning an abandoned factory in Central Europe into a large datacenter, even though the area has very little existing fiber infrastructure.

RETN's warning is that network connections must be planned at the same time as electricity supplies and building work. Developers should not leave this until the datacenter is almost ready to open. ®