SpaceX has named its planned supercomputer campus in southeastern Arizona Colossus 3.

The aerospace company, founded by Elon Musk, bought xAI early this year in a merger valued at $1 trillion. The company wants to build the third in a series of huge groups of data centers. These centers train advanced artificial intelligence models, such as Grok. Colossus 3 would be built near Willcox Playa in Cochise County.

"SpaceX Colossus 3 will greatly benefit the Arizona community," Musk wrote on X on Nov. 25. He was responding to a company post that explained plans for the $50 billion project.

SpaceX said the 747-acre campus was "designed with Arizona in mind." The company says it will not use gas-fired power plants or industrial water. When fully built, the large AI-training facility could need up to 6 gigawatts of electricity.

Local reaction to the data center is mixed

Arizona residents filled a community meeting on Nov. 6. Company employees explained the project at the meeting. SpaceX said it would build and operate the project. However, the application that will go before the Cochise County zoning and planning commission on Dec. 9 is still under the name Tombstone Resources LLC. A Houston-based AI lobbyist named Soroosh Fegh started the Wyoming company this year.

Some people shouted and booed as soon as the SpaceX team began its presentation. Other residents were hopeful about the project. They said the large amount of tax money it could bring might help their community. They also liked the company's promises of more jobs, lower property taxes and lower electricity bills. Most changes to electricity rates must be approved by the Arizona Corporation Commission.

In its application for special permission from the county zoning commission, Tombstone Resources LLC said the project would be built in four stages. It could include as many as nine buildings for computing. The campus would use a cooling system that does not rely on water. It would not pump groundwater for industrial use. An existing well would pump up to 10 acre-feet of water each year from the underground water supply. This water would be used for drinking, maintenance and cleaning equipment.

An electricity service agreement filed with the Arizona Corporation Commission says the company would work with utility providers to get power from across the Southwest. SpaceX would pay for its electricity and service costs. It would also pay in advance for improvements to the power network. In a letter to the commission, the company said it would not build a power plant that burns natural gas.

The coal-fired Apache Generating Station produces about one-tenth of the electricity the fully built project could need. However, it is not expected to supply power to the project. SpaceX has not publicly explained where it plans to get the large amount of electricity it will need.

Arizona Electric Power Cooperative Inc. filed an application with the Arizona Corporation Commission in April. The cooperative wants to create a "standardized, streamlined process" for reviewing and approving electricity service agreements for large customers interested in building projects in rural Arizona. These customers include data centers, greenhouses, factories and other industrial businesses.

"In response to current inquiries and in anticipation that more inquiries will follow, the Cooperatives are coordinating efforts to ensure they are prepared to provide safe, reliable, and affordable electric service to these businesses in a way that will promote local investment and protect the affordability and reliability of service for existing retail members," the application said.

Attorney general asks for a delay, but company disagrees

The application does not say how long construction will take. However, SpaceX employees told residents that the company hopes to begin building the first phase next spring if it gets all the required permits. According to xAI, the first Colossus group of data centers in Memphis, Tennessee, was built six times faster than expected.

"We took the project into our own hands, questioned everything, removed whatever was unnecessary, and accomplished our goal in four months," the company's website says.

If the zoning commission approves the application, the company will be responsible for clearing and leveling the land, building highway access and drainage systems, getting environmental approvals and obtaining building permits. The project will also need environmental approval from the Arizona Department of Environmental Quality and the Arizona Department of Water Resources. It will likely need permission from a federal agency that protects wildlife, too.

Arizona Attorney General Kris Mayes asked the planning and zoning commission to delay the hearing scheduled for Dec. 9.

"The company’s proposal raises serious unanswered questions about energy reliability, water use, emergency response capabilities, traffic impacts, and effects on surrounding communities," she wrote in a letter on Nov. 19. She also said the campus could interfere with military testing and training near Willcox Playa.

"Those issues must be fully examined by the appropriate state and federal agencies before any local approval moves forward."

SpaceX responded to Mayes' letter on Nov. 24. The company asked the commission to hold the public hearing and "consider SU26-22 on its merits." It also said that Tombstone Resources LLC, the company named in the application, is "a wholly owned subsidiary of SpaceX." The letter included new details about the project's power sources, cooling system and emergency response plans, among other subjects.

Cochise County has not announced any changes to the scheduled hearing. Mayes plans to hold a town hall meeting in Cochise on Dec. 3 to hear residents' concerns.